Electric vehicles, design stage

Part S EV Charging Calculator

How many electric vehicle charge points and cable routes a scheme needs under Approved Document S and regulations 44D to 44J.

Six requirements, each with its own trigger. The tool asks only the questions the applicable one needs: the £3600 connection cost cap belongs to new residential work, the 7% cost cap to major renovations, and covered car parks change the answer everywhere.

Everything is calculated on this device. When you download a report or save a file, any supplied contact and project details are sent securely to Briary and retained separately from anonymous Tool Insights; calculation values are not retained. Read our tool privacy information.

The right requirement

S1 to S6, each routed to its own regulation, with mixed use running both branches and adding the answers.

Both caps

The £3600 average connection cost on new residential work and the 7% of renovation cost on major renovations.

The full specification

7 kW untethered charge points, cable route standards, the label size and the clear space at each position.

The work Requirement S1

Regulation 44D of the Building Regulations 2010.

Residential parking 0 charge points
The £3600 connection cost cap Regulation 44D(2)

To rely on the cap, paragraph 1.7 requires at least two formal quotes at notice or plans stage, at least one of them from a distribution network operator.

Check a proposed schedule Optional
What each charge point has to be Paragraph 6.2
    Project and your details Needed for the PDF

    The name and company are printed on the PDF report and are needed before it can be produced. Everything else here is optional and is printed only if you supply it.

    Method, data and scope

    Approved Document S applies in England and took effect on 15 June 2022. Part S turns on facts a calculator cannot see: which parking spaces are associated with the building, where the site boundary runs, whether a car park is covered, whether the incoming supply has capacity, and what a distribution network operator will quote. Every figure here follows from the numbers entered, and a competent person must establish those numbers. Approved Document S gives no guidance on electrical or fire safety; Approved Documents B and P, the Electricity at Work Regulations 1989, BS 7671 and the IET Code of Practice all apply to the same installation.

    How to use this tool

    Start here, then keep the guide open alongside your work. Expand a section for the information you need.

    Before you start

    Establish which requirement applies and, above all, which parking spaces are associated with the building. That is the input most likely to be wrong, and Diagrams 1.1 and 1.2 of Approved Document S exist for that reason. A space is associated if it is within the site boundary and for the use of the occupants or users of the building. A space beyond a public highway or on someone else’s land is not. Some garages contain no parking space at all.

    1. Pick the type of work

    S1 for a new residential building, S2 for a material change of use creating dwellings, S3 for a residential major renovation, S4 for a new non-residential building, S5 for a non-residential major renovation, S6 for mixed use. The tool then asks only the questions that requirement needs. S3, S4 and S5 are engaged only where there will be more than 10 parking spaces.

    2. Enter the parking

    Associated spaces, how many of those are in a covered car park, and how many dwellings the parking serves. Paragraph 1.1 sets the residential requirement at the lesser of the spaces and the dwellings, so a house with two spaces on the drive needs one charge point, and a block of 10 flats sharing 4 spaces needs four.

    3. Covered car parks

    Charge points are not required in a covered car park. The requirement is met by putting them in the spaces that are not covered first, and cable routes then make up the rest of the total. Where every space is covered, no charge point is required at all — but cable routes still are, and for a residential building with more than 10 spaces that means every space.

    4. The two cost caps

    The £3600 average connection cost cap applies to new residential work. To rely on it, paragraph 1.7 requires at least two formal quotes at notice or plans stage, at least one from a distribution network operator, and you enter the maximum number installable within the cap. The 7% cap applies to major renovations: under it everything applies, over it the charge points fall away but cable routes remain, and over it even for cable routes alone nothing is required.

    5. Check the schedule

    Enter what the drawings show and the tool says whether it is enough. A charge point may serve more than one space provided all those spaces can be used for recharging at the same time, so count outlets rather than enclosures. Where the building has accessible parking, paragraph 6.4 requires at least one accessible space to have a charge point or a future connection location.

    What is outside this tool

    Approved Document S gives no guidance on electrical or fire safety. Approved Documents B and P, the Electricity at Work Regulations 1989, BS 7671 and the IET Code of Practice all apply to the same installation. Whether the incoming supply has capacity, and what a distribution network operator will quote, are matters of evidence the tool cannot establish.

    PDF, saving and support

    The PDF needs your name and company. It records the requirement, the regulation, the working and the full specification for charge points and cable routes. Save inputs writes a .briaryev file. For problems, email toolsuite@briary.co.uk.

    Need the Part S schedule signed off?

    Send the site layout, the parking arrangement and any distribution network operator quotes.

    Request Part S support